top of page

Hutton Construction Ltd v Wilson Properties (London) Ltd

Citation: [2017] EWHC 517 (TCC)

Background Facts​

  • The dispute arose from the conversion of Danbury Palace in Chelmsford into apartments, under a JCT Standard Building Contract.

  • Hutton submitted Application for Payment No. 24 on 17 August 2016, for a substantial sum.

  • The key dispute was whether Wilson served a valid Pay Less Notice in response.

  • In adjudication, Hutton was awarded £491,944.73 after the adjudicator found that Wilson’s Pay Less Notice was invalid.

  • Hutton sought summary judgment to enforce the adjudicator’s award.

  • Wilson tried to resist enforcement by arguing, through a Part 8 claim, that its Pay Less Notice was in fact a valid interim certificate, and thus valid.

​Judgment

  • Court’s decision:

    • The court granted summary judgment to Hutton, enforcing the adjudicator’s decision in full.

​

  • Key findings:

    • The defendant’s arguments did not fall within the narrow exceptions to immediate enforcement.

    • The challenge attempted to re-argue the issues already determined in adjudication, including detailed factual matters and contract interpretation.

    • The defendant’s Part 8 claim was too broad and introduced new factual contentions, making it unsuitable for resolution at a summary enforcement hearing.

    • The judge emphasised that the principles of adjudication aim for quick cash flow decisions and do not allow a defeated party to re-litigate substantive disputes at enforcement stage.

​

  • Outcome:

    • Judgment entered for Hutton in the sum of £491,944.73 to be paid within 7 days.

    • Wilson was allowed to pursue its Part 8 claim separately through proper court procedure but could not use it to resist immediate payment.

General Principles Developed

  • Strict enforcement of adjudication decisions:

    • Adjudicator’s decisions will be enforced promptly unless there is a clear lack of jurisdiction or a breach of natural justice.

    • The correctness of the adjudicator’s decision (even if arguably wrong) is irrelevant to enforcement.

​

  • Limited scope for challenges at enforcement:

    • Defendants cannot resist payment merely by asserting the adjudicator was wrong; they must meet high thresholds for exceptions.

    • Only narrow, self-contained points suitable for short, evidence-light hearings (e.g., pure legal interpretation clearly determinative) may be raised.

​

  • Separate route for substantive challenges:

    • Parties wishing to challenge the correctness of a decision must do so in separate proceedings (e.g., via Part 8 claims), not as a defence to enforcement.

    • The existence of a separate challenge does not justify withholding payment ordered by an adjudicator.

​

  • "Pay now, argue later" policy reaffirmed:

    • Reinforces the cash flow-focused intent of the Construction Act 1996 and the “pay now, argue later” approach.

​

  • Indemnity costs warning:

    • Abusive or improper attempts to resist enforcement may result in indemnity costs orders against the resisting party.

bottom of page