top of page

J Murphy & Sons Ltd v W Maher and Sons Ltd

Citation: [2016] EWHC 1148 (TCC)

Background Facts​

  • Murphy was engaged by Balfour Beatty to carry out shaft and tunnel work at Trafford Park, Manchester.

  • Murphy subcontracted Maher in February 2014 to remove spoil and supply aggregate.

  • Maher submitted a final account application in September 2015 for ~£764,000, claiming a net balance due of ~£297,000.

  • On 11 November 2015, it was alleged that Maher and Murphy orally agreed a final account sum of £720,000, implying a payment of £253,169 outstanding.

  • Murphy initially acknowledged this agreement but later disputed it, valuing the work much lower at £483,000 and refusing further payment.

  • Maher served a Notice of Adjudication in April 2016 to recover the agreed sum.

  • Murphy challenged the adjudicator’s jurisdiction, arguing the dispute arose under a separate "settlement agreement" and not under the subcontract.

​Judgment

  • Decision:

    • The court rejected Murphy’s jurisdiction challenge and ruled the dispute could properly be adjudicated.

​

  • Key findings:

    • The adjudication clause in the subcontract covered disputes “arising under or in connection with” the subcontract, which is sufficiently broad.

    • Even if there was a final account agreement, it arose directly in connection with the original subcontract.

    • The alleged oral agreement was either a variation to the subcontract or at least a settlement of a claim arising under it, so it remained within adjudication scope.

​

  • Declaration:

    • The court granted a declaration confirming that the adjudicator had jurisdiction to decide the dispute.

​

  • Outcome:

    • Murphy’s Part 8 claim was dismissed.

    • Murphy was ordered to pay Maher’s costs (£11,000).

General Principles Developed

  • Broad interpretation of adjudication clauses:

    • Where contracts include words such as “in connection with,” adjudication jurisdiction extends beyond strict contractual terms to related agreements or settlements.

​

  • Settlement agreements and variations:

    • An alleged final account or settlement agreement resolving claims under a contract is typically treated as arising “under” or “in connection with” that contract.

    • Disputes about whether such agreements exist or are binding can still be referred to adjudication.

​

  • Commercial purpose of adjudication:

    • The policy of the Construction Act 1996 (and similar to arbitration) supports an inclusive approach, enabling speedy resolution of cash flow disputes.

    • Parties are assumed to want all disputes arising from their contractual relationship resolved in a single, consistent forum (adjudication).

​

  • No strict division between “under” and “in connection with”:

    • The decision confirms the approach taken in Fiona Trust (arbitration context) should inform construction adjudication, avoiding artificial distinctions.

​

  • Practical approach to subcontract administration:

    • Final account discussions, even if intended to close out a project, remain subject to adjudication if a dispute arises about their validity or effect.

bottom of page