
J Murphy & Sons Ltd v W Maher and Sons Ltd
Citation: [2016] EWHC 1148 (TCC)
Background Facts​
-
Murphy was engaged by Balfour Beatty to carry out shaft and tunnel work at Trafford Park, Manchester.
-
Murphy subcontracted Maher in February 2014 to remove spoil and supply aggregate.
-
Maher submitted a final account application in September 2015 for ~£764,000, claiming a net balance due of ~£297,000.
-
On 11 November 2015, it was alleged that Maher and Murphy orally agreed a final account sum of £720,000, implying a payment of £253,169 outstanding.
-
Murphy initially acknowledged this agreement but later disputed it, valuing the work much lower at £483,000 and refusing further payment.
-
Maher served a Notice of Adjudication in April 2016 to recover the agreed sum.
-
Murphy challenged the adjudicator’s jurisdiction, arguing the dispute arose under a separate "settlement agreement" and not under the subcontract.
​Judgment
-
Decision:
-
The court rejected Murphy’s jurisdiction challenge and ruled the dispute could properly be adjudicated.
-
​
-
Key findings:
-
The adjudication clause in the subcontract covered disputes “arising under or in connection with” the subcontract, which is sufficiently broad.
-
Even if there was a final account agreement, it arose directly in connection with the original subcontract.
-
The alleged oral agreement was either a variation to the subcontract or at least a settlement of a claim arising under it, so it remained within adjudication scope.
-
​
-
Declaration:
-
The court granted a declaration confirming that the adjudicator had jurisdiction to decide the dispute.
-
​
-
Outcome:
-
Murphy’s Part 8 claim was dismissed.
-
Murphy was ordered to pay Maher’s costs (£11,000).
-
General Principles Developed
-
Broad interpretation of adjudication clauses:
-
Where contracts include words such as “in connection with,” adjudication jurisdiction extends beyond strict contractual terms to related agreements or settlements.
-
​
-
Settlement agreements and variations:
-
An alleged final account or settlement agreement resolving claims under a contract is typically treated as arising “under” or “in connection with” that contract.
-
Disputes about whether such agreements exist or are binding can still be referred to adjudication.
-
​
-
Commercial purpose of adjudication:
-
The policy of the Construction Act 1996 (and similar to arbitration) supports an inclusive approach, enabling speedy resolution of cash flow disputes.
-
Parties are assumed to want all disputes arising from their contractual relationship resolved in a single, consistent forum (adjudication).
-
​
-
No strict division between “under” and “in connection with”:
-
The decision confirms the approach taken in Fiona Trust (arbitration context) should inform construction adjudication, avoiding artificial distinctions.
-
​
-
Practical approach to subcontract administration:
-
Final account discussions, even if intended to close out a project, remain subject to adjudication if a dispute arises about their validity or effect.
-