top of page

Carillion Construction Ltd v Devonport Royal Dockyard Ltd

Citation: [2005] EWCA Civ 1358

Background Facts​

  • Carillion Construction Ltd ("Carillion") was the subcontractor and Devonport Royal Dockyard Ltd ("DML") the main contractor, engaged to refit nuclear submarines.

  • DML had a main contract with the Ministry of Defence (MoD) to upgrade Devonport dockyard facilities.

  • Carillion was engaged as a subcontractor to upgrade "9 Dock" including major civil engineering works.

  • Their relationship was governed by a subcontract and a detailed Alliance Agreement, which included a "target cost" payment mechanism with gain/pain share provisions.

  • Amendments to the target cost were made during the works; final costs and bonuses were disputed.

  • Carillion claimed over £10 million in further payments and a £1.5 million bonus.

  • An adjudicator ruled in Carillion’s favour, awarding over £10 million.

  • DML resisted enforcement, arguing lack of jurisdiction, breach of natural justice, and inadequate reasoning.

​Judgment

  • Court of Appeal decision:

    • The adjudicator’s decision was upheld as valid and enforceable.

    • DML's arguments that the adjudicator had exceeded jurisdiction or breached natural justice were rejected.

​

  • Key points:

    • Adjudicators’ decisions must generally be enforced even if there are factual or legal errors, as they are intended to be temporarily binding.

    • The adjudicator was acting within jurisdiction: assessing the target cost was integral to determining the sums payable under the Alliance Agreement.

    • No serious breach of natural justice occurred, despite DML’s complaints about process and reasoning.

    • Brief reasons given by an adjudicator suffice as long as they cover the issues and allow parties to understand the decision.

​

  • Outcome:

    • Carillion obtained summary judgment enforcing the adjudicator's award of approximately £10.6 million.

General Principles Developed

  • Enforceability of adjudication decisions:

    • Reinforced the "pay now, argue later" policy of the Housing Grants, Construction and Regeneration Act 1996.

    • Errors of fact, law, or procedure do not prevent enforcement unless they constitute jurisdictional errors or serious breaches of natural justice.

​

  • Natural justice threshold:

    • Breaches must be serious (e.g., a party denied opportunity to present its case) to resist enforcement.

    • Procedural imperfections or errors in reasoning do not amount to serious breaches.

​

  • Jurisdictional approach:

    • The scope of an adjudicator’s jurisdiction is defined by the dispute referred in the notice of adjudication.

    • When resolving a referred dispute, the adjudicator can address issues necessarily linked to that dispute.

​

  • Role of reasons:

    • Adjudicators are not required to give detailed reasons; short, intelligible explanations suffice.

​

  • Judicial attitude:

    • Courts discourage technical challenges to adjudicator decisions, favouring quick enforcement to preserve cash flow in construction projects.

bottom of page