
Carillion Construction Ltd v Devonport Royal Dockyard Ltd
Citation: [2005] EWCA Civ 1358
Background Facts​
-
Carillion Construction Ltd ("Carillion") was the subcontractor and Devonport Royal Dockyard Ltd ("DML") the main contractor, engaged to refit nuclear submarines.
-
DML had a main contract with the Ministry of Defence (MoD) to upgrade Devonport dockyard facilities.
-
Carillion was engaged as a subcontractor to upgrade "9 Dock" including major civil engineering works.
-
Their relationship was governed by a subcontract and a detailed Alliance Agreement, which included a "target cost" payment mechanism with gain/pain share provisions.
-
Amendments to the target cost were made during the works; final costs and bonuses were disputed.
-
Carillion claimed over £10 million in further payments and a £1.5 million bonus.
-
An adjudicator ruled in Carillion’s favour, awarding over £10 million.
-
DML resisted enforcement, arguing lack of jurisdiction, breach of natural justice, and inadequate reasoning.
​Judgment
-
Court of Appeal decision:
-
The adjudicator’s decision was upheld as valid and enforceable.
-
DML's arguments that the adjudicator had exceeded jurisdiction or breached natural justice were rejected.
-
​
-
Key points:
-
Adjudicators’ decisions must generally be enforced even if there are factual or legal errors, as they are intended to be temporarily binding.
-
The adjudicator was acting within jurisdiction: assessing the target cost was integral to determining the sums payable under the Alliance Agreement.
-
No serious breach of natural justice occurred, despite DML’s complaints about process and reasoning.
-
Brief reasons given by an adjudicator suffice as long as they cover the issues and allow parties to understand the decision.
-
​
-
Outcome:
-
Carillion obtained summary judgment enforcing the adjudicator's award of approximately £10.6 million.
-
General Principles Developed
-
Enforceability of adjudication decisions:
-
Reinforced the "pay now, argue later" policy of the Housing Grants, Construction and Regeneration Act 1996.
-
Errors of fact, law, or procedure do not prevent enforcement unless they constitute jurisdictional errors or serious breaches of natural justice.
-
​
-
Natural justice threshold:
-
Breaches must be serious (e.g., a party denied opportunity to present its case) to resist enforcement.
-
Procedural imperfections or errors in reasoning do not amount to serious breaches.
-
​
-
Jurisdictional approach:
-
The scope of an adjudicator’s jurisdiction is defined by the dispute referred in the notice of adjudication.
-
When resolving a referred dispute, the adjudicator can address issues necessarily linked to that dispute.
-
​
-
Role of reasons:
-
Adjudicators are not required to give detailed reasons; short, intelligible explanations suffice.
-
​
-
Judicial attitude:
-
Courts discourage technical challenges to adjudicator decisions, favouring quick enforcement to preserve cash flow in construction projects.
-