
Toppan Holdings Ltd & Anor v Simply Construct (UK) LLP
Citation: [2021] EWHC 2110 (TCC)
Background Facts​
-
Simply Construct built Aarandale Manor Care Home under a JCT Design and Build Contract (c. £4.7 million).
-
Practical completion was in October 2016. Toppan later discovered serious fire safety defects in 2018.
-
Remedial works were carried out by others in 2019–2020.
-
A novation transferred the building contract from Sapphire to Toppan in 2017.
-
In October 2020, after significant delays and pressure, Simply signed a collateral warranty in favour of Abbey.
-
Abbey and Toppan commenced separate adjudications in 2020 seeking damages for defects.
-
Toppan adjudication: Toppan awarded £1.07 million for remedial works and costs.
-
Abbey adjudication: Abbey awarded £908,495 for loss of trading profit.
-
Toppan and Abbey sought summary judgment to enforce the adjudication awards.
​Judgment
-
Toppan adjudication:
-
The court enforced the Toppan adjudicator’s award in full.
-
​​
-
Abbey adjudication:
-
The court held that Abbey’s collateral warranty was not a “construction contract” under the Housing Grants, Construction and Regeneration Act 1996, section 104.
-
-
Therefore, the adjudicator lacked jurisdiction in Abbey’s adjudication, and enforcement was refused.
​​
-
Key points:
-
The Abbey warranty was signed four years after practical completion and after all remedial works had been completed.
-
The warranty was mainly a warranty of past performance rather than an agreement for carrying out future works, meaning it did not fall within the Act’s definition of a “construction contract.”
-
​​
-
Interest and VAT:
-
The court upheld the adjudicator’s award of interest and VAT in Toppan’s case as no jurisdictional objections were raised.
-
The court found Toppan was entitled to VAT recovery.
-
​​
-
Stay of execution:
-
Simply requested a stay of execution, alleging that Toppan and Abbey might not be able to repay the sums if overpaid.
-
The court rejected the stay application for Toppan, finding Toppan financially sound.
-
The Abbey claim was not enforced, so no stay issue arose.
-
General Principles Developed
-
Collateral warranties and adjudication rights:
-
Not all collateral warranties are “construction contracts.” A warranty is unlikely to be a construction contract if:
-
All works are completed long before execution.
-
It merely warrants past performance rather than promising future construction obligations.
-
-
​
-
Timing matters:
-
Execution timing is critical. A warranty given after completion and after remedial works are finished will usually be treated as only confirming a past state of affairs.
-
​
-
Jurisdiction objections:
-
Objections to adjudicator jurisdiction (e.g., whether an agreement is a construction contract) must be properly raised. Otherwise, participation may imply acceptance of jurisdiction.
-
​
-
Enforcement approach:
-
Courts strongly support enforcing valid adjudicator decisions swiftly to preserve cash flow, reflecting the “pay now, argue later” principle.
-
​
-
Stay of execution tests:
-
Financial ability to repay is a key consideration.
-
Even where a claimant has a questionable financial history, evidence of group support and stable trading can defeat stay applications.
-