top of page

Jerram Falkus Construction Ltd v Fenice Investments Inc

Citation: [2011] EWHC 1935 (TCC)

Background Facts​

  • Jerram Falkus Construction Ltd (JFC) a contractor and Fenice Investments Inc, an employer entered into a contract regarding a development at 150 Loudoun Road, London. The contract was a JCT Design and Build Contract 2005 with amendments.

  • Contractual completion date extended to 15 June 2009, actual completion was 9 September 2009 (86 days late).

  • Fenice claimed liquidated damages for delay.

  • JFC argued delays were due to Fenice’s acts of prevention, setting time at large and removing Fenice’s entitlement to liquidated damages. JFC also claimed loss and expense.

  • A prior adjudication decision (the third adjudication) had rejected JFC’s prevention arguments.

  • JFC also claimed a final account balance of £311,393.78, arguing Fenice had failed to challenge it properly.

​Judgment

  • Conclusive effect of adjudication:

    • The third adjudication decision, which rejected JFC’s prevention arguments, had not been challenged within 28 days and was therefore conclusive per clause 1.9.4 of the contract.

    • JFC was barred from re-litigating those prevention and extension of time arguments.

​

  • Final account conclusivity:

    • Fenice's detailed challenge letter dated 24 January 2011 prevented JFC's final account from becoming conclusive.

    • The final account could therefore still be contested in court, and JFC's argument for automatic payment of the claimed balance failed.

​

  • Delay and prevention arguments:

    • Delays were caused primarily by JFC’s own failures (e.g., design errors, delayed preparation for statutory undertakers, levels problem in houses).

    • Fenice did not act in a way that triggered the prevention principle; no acts prevented JFC from timely completion.

​

  • Liquidated damages:

    • Fenice entitled to recover liquidated damages of £209,840 gross (£122,102 net).

​

  • Alleged oral agreement to reduce LADs:

    • Court found no binding agreement to discount liquidated damages.

General Principles Developed

  • Conclusive adjudication decisions:

    • An adjudicator’s decision becomes conclusive if not challenged in arbitration or litigation within the contractually required timeframe.

​

  • Effect of prevention principle and concurrency:

    • Prevention principle only applies if employer’s act alone caused delay that prevented completion.

    • Concurrent delays for which the contractor is responsible negate prevention claims.

​

  • Conclusive effect of final account statements:

    • Employer’s detailed and timely challenge prevents a contractor’s final account from becoming conclusive under JCT terms.

    • "Conclusive" means final settlement on items unless properly disputed.

​

  • Interpretation of contract provisions:

    • Courts take a practical, commercially sensible approach to interpretation, avoiding artificial or rigid readings that frustrate contract purpose.

​

  • Approach to delay analysis:

    • Courts require careful factual analysis to allocate responsibility for delays and resist broad assertions of prevention without clear causative evidence.

​

  • Settlement and partial agreements:

    • Informal or "without prejudice" discussions cannot constitute binding variation of LAD provisions without clear agreement on essential terms.

bottom of page