
Jerram Falkus Construction Ltd v Fenice Investments Inc
Citation: [2011] EWHC 1935 (TCC)
Background Facts​
-
Jerram Falkus Construction Ltd (JFC) a contractor and Fenice Investments Inc, an employer entered into a contract regarding a development at 150 Loudoun Road, London. The contract was a JCT Design and Build Contract 2005 with amendments.
-
Contractual completion date extended to 15 June 2009, actual completion was 9 September 2009 (86 days late).
-
Fenice claimed liquidated damages for delay.
-
JFC argued delays were due to Fenice’s acts of prevention, setting time at large and removing Fenice’s entitlement to liquidated damages. JFC also claimed loss and expense.
-
A prior adjudication decision (the third adjudication) had rejected JFC’s prevention arguments.
-
JFC also claimed a final account balance of £311,393.78, arguing Fenice had failed to challenge it properly.
​Judgment
-
Conclusive effect of adjudication:
-
The third adjudication decision, which rejected JFC’s prevention arguments, had not been challenged within 28 days and was therefore conclusive per clause 1.9.4 of the contract.
-
JFC was barred from re-litigating those prevention and extension of time arguments.
-
​
-
Final account conclusivity:
-
Fenice's detailed challenge letter dated 24 January 2011 prevented JFC's final account from becoming conclusive.
-
The final account could therefore still be contested in court, and JFC's argument for automatic payment of the claimed balance failed.
-
​
-
Delay and prevention arguments:
-
Delays were caused primarily by JFC’s own failures (e.g., design errors, delayed preparation for statutory undertakers, levels problem in houses).
-
Fenice did not act in a way that triggered the prevention principle; no acts prevented JFC from timely completion.
-
​
-
Liquidated damages:
-
Fenice entitled to recover liquidated damages of £209,840 gross (£122,102 net).
-
​
-
Alleged oral agreement to reduce LADs:
-
Court found no binding agreement to discount liquidated damages.
-
General Principles Developed
-
Conclusive adjudication decisions:
-
An adjudicator’s decision becomes conclusive if not challenged in arbitration or litigation within the contractually required timeframe.
-
​
-
Effect of prevention principle and concurrency:
-
Prevention principle only applies if employer’s act alone caused delay that prevented completion.
-
Concurrent delays for which the contractor is responsible negate prevention claims.
-
​
-
Conclusive effect of final account statements:
-
Employer’s detailed and timely challenge prevents a contractor’s final account from becoming conclusive under JCT terms.
-
"Conclusive" means final settlement on items unless properly disputed.
-
​
-
Interpretation of contract provisions:
-
Courts take a practical, commercially sensible approach to interpretation, avoiding artificial or rigid readings that frustrate contract purpose.
-
​
-
Approach to delay analysis:
-
Courts require careful factual analysis to allocate responsibility for delays and resist broad assertions of prevention without clear causative evidence.
-
​
-
Settlement and partial agreements:
-
Informal or "without prejudice" discussions cannot constitute binding variation of LAD provisions without clear agreement on essential terms.
-