
A & V Building Solution Ltd v J & B Hopkins Ltd
Citation: [2024] EWHC 1510 (TCC)
Background Facts
-
The project was for plumbing works for the Moulsecoomb Campus student accommodation for the University of Brighton.
-
Main contractor: Bouygues UK; JBH was a subcontractor; A&V was engaged under a sub-subcontract dated 18 December 2019 for Towers 1–3 and Podiums 1 and 2.
-
The contract sum was initially £368,000 and later increased to £447,800 due to variations.
-
A&V began works in early 2020; site temporarily closed due to COVID-19 in March 2020.
-
There were delays and resequencing of works, especially in the Podiums.
-
By March 2021, A&V left site with works incomplete. JBH claimed this was due to poor performance; A&V claimed delays were caused by JBH and external factors.
-
Dispute arose over the final account, valuation of completed works, variations, and responsibility for delays and costs.
Judgment
-
Key findings:
-
A&V did not complete the works and left site before finishing, breaching the subcontract.
-
Although there were delays and resequencing issues (partly due to BYUK and COVID-19), A&V was still contractually required to complete on time or seek proper extensions, which it did not do adequately.
-
A&V’s claims for additional losses (over £645,000) were largely rejected.
-
JBH’s contra charges and costs (e.g., for completing the works and rectifying defects) were allowed.
-
​
-
Outcome:
-
The court substantially sided with JBH’s valuation.
-
A&V was found liable for the cost of incomplete and defective works, as well as the costs JBH incurred to complete.
-
A&V’s claim for further payment was dismissed, and it was ordered to pay JBH a net sum after set-off.
-
General Principles Developed
-
Strict compliance with contract obligations:
Even when external delays occur (e.g., resequencing or COVID), a subcontractor must formally notify and seek extensions in accordance with contract terms.
​
-
Importance of evidence and contemporaneous records:
The court relied heavily on documentation (e.g., emails, minutes, records of handovers) over retrospective assertions.
​
-
Responsibility for site logistics and progress:
Subcontractors remain responsible for coordinating and completing works diligently, even in challenging conditions. Failure to proceed "regularly and diligently" may justify employer termination or recovery of completion costs.
​
-
Objective valuation of final accounts:
Final account valuations are determined objectively based on measured work, certified variations, and rectification costs, rather than subjective or inflated claims.
​
-
No recovery without substantiation:
Claims for variations or additional losses require clear substantiation and compliance with contract procedures (e.g., clause requiring detailed supporting information as condition precedent to payment).