top of page

A & V Building Solution Ltd v J & B Hopkins Ltd

Citation: [2024] EWHC 1510 (TCC)

Background Facts

  • The project was for plumbing works for the Moulsecoomb Campus student accommodation for the University of Brighton.

  • Main contractor: Bouygues UK; JBH was a subcontractor; A&V was engaged under a sub-subcontract dated 18 December 2019 for Towers 1–3 and Podiums 1 and 2.

  • The contract sum was initially £368,000 and later increased to £447,800 due to variations.

  • A&V began works in early 2020; site temporarily closed due to COVID-19 in March 2020.

  • There were delays and resequencing of works, especially in the Podiums.

  • By March 2021, A&V left site with works incomplete. JBH claimed this was due to poor performance; A&V claimed delays were caused by JBH and external factors.

  • Dispute arose over the final account, valuation of completed works, variations, and responsibility for delays and costs.

Judgment

  • Key findings:

    • A&V did not complete the works and left site before finishing, breaching the subcontract.

    • Although there were delays and resequencing issues (partly due to BYUK and COVID-19), A&V was still contractually required to complete on time or seek proper extensions, which it did not do adequately.

    • A&V’s claims for additional losses (over £645,000) were largely rejected.

    • JBH’s contra charges and costs (e.g., for completing the works and rectifying defects) were allowed.

​

  • Outcome:

    • The court substantially sided with JBH’s valuation.

    • A&V was found liable for the cost of incomplete and defective works, as well as the costs JBH incurred to complete.

    • A&V’s claim for further payment was dismissed, and it was ordered to pay JBH a net sum after set-off.

General Principles Developed

  • Strict compliance with contract obligations:
    Even when external delays occur (e.g., resequencing or COVID), a subcontractor must formally notify and seek extensions in accordance with contract terms.

​

  • Importance of evidence and contemporaneous records:
    The court relied heavily on documentation (e.g., emails, minutes, records of handovers) over retrospective assertions.

​

  • Responsibility for site logistics and progress:
    Subcontractors remain responsible for coordinating and completing works diligently, even in challenging conditions. Failure to proceed "regularly and diligently" may justify employer termination or recovery of completion costs.

​

  • Objective valuation of final accounts:
    Final account valuations are determined objectively based on measured work, certified variations, and rectification costs, rather than subjective or inflated claims.

​

  • No recovery without substantiation:
    Claims for variations or additional losses require clear substantiation and compliance with contract procedures (e.g., clause requiring detailed supporting information as condition precedent to payment).

bottom of page