top of page

Workman Properties Ltd v Adi Building And Refurbishment Ltd

Citation: [2024] EWHC 2627 (TCC)

Background Facts​

  • The project involved the expansion works at Cotteswold Dairy, Tewkesbury, including new cold stores, offices, regrading of yard, and new drainage.

  • JCT Design and Build Contract 2016 (with bespoke amendments), signed January 2022.

  • Employer’s Requirements stated that design had been developed up to RIBA Stage 4 or 4(i).

  • ADI argued that design information provided by WPL was incomplete and not fully developed to RIBA Stage 4/4(i), causing extra work, time, and cost.

  • An adjudicator (Mr Hough) found in ADI’s favor on the interpretation that WPL had warranted the design was complete to Stage 4/4(i), entitling ADI to damages and to treat additional design work as a Change under the contract.

  • WPL then brought Part 8 proceedings seeking court declarations clarifying its design obligations.

​Judgment

  • Court’s decision:

    • The court favoured WPL’s interpretation, overturning the adjudicator’s view.

​

  • Key findings:

    • Under the contract, ADI had full responsibility for all design, including design within the Employer’s Requirements.

    • The contract and its bespoke amendments placed the onus on ADI to verify, complete, and accept responsibility for all design, whether or not it had been developed to RIBA Stage 4/4(i).

    • The Employer’s Requirements stating that design had been developed to Stage 4/4(i) did not constitute a warranty but rather described the state of development; they did not absolve ADI of responsibility.

    • ADI was required to satisfy itself that the design was sufficient for construction and was contractually responsible for any gaps or deficiencies.

​

  • Declarations granted:

    • ADI was obliged to complete all design work to RIBA Stage 4/4(i).

    • WPL did not warrant that design was fully developed to Stage 4/4(i).

    • ADI could not treat further design work as a Change, nor claim additional time, costs, or loss/expense on that basis.

​

  • Outcome:
    The court granted limited declarations reflecting these points but rejected broader and overly wide declarations sought by WPL.

General Principles Developed

  • Design responsibility in design and build contracts:

    • When a design and build contractor assumes full design responsibility, it accepts the risk of incomplete or defective design in Employer’s Requirements unless expressly excluded.

​

  • Interpretation of design stage statements:

    • Statements describing design progress (e.g., "developed to Stage 4") are not warranties unless clearly stated as such.

    • Contractors must independently verify sufficiency and completeness of any prior design before proceeding.

​

  • Effect of bespoke amendments:

    • Contractual amendments placing full design liability on the contractor override general expectations from standard form wording.

​

  • No implied warranties without clear language:

    • Courts will not infer a warranty or representation about design completeness unless explicitly included in the contract language.

​

  • Role of Part 8 proceedings:

    • Suitable for resolving pure points of contractual interpretation not requiring resolution of disputed facts.

bottom of page