top of page

Whiteways Contractors (Sussex) Ltd v Impresa Castelli Construction Ltd

Citation: [2000] EWHC Technology 67

Background Facts​

  • Whiteways was subcontracted under DOM/1 standard subcontract conditions (with adjudication clause 38A).

  • After an earlier adjudication and payment, Whiteways referred a second dispute in January 2000 relating to unpaid sums from its final account, prolongation costs, interest, financing charges, and interim applications 22 and 23.

  • The adjudicator (Mr. Murphy) decided Whiteways was owed £81,177.45 plus VAT (£95,383.50 total).

  • The defendant refused to pay, alleging the adjudicator exceeded jurisdiction and wrongly dealt with issues not properly referred.

​Judgment

  • Court decision:

    • Summary judgment granted for Whiteways, enforcing the adjudicator’s decision in full.

​

  • Key findings:

    • The adjudicator had jurisdiction:

      • The court found that the Notice of Adjudication sufficiently identified the disputes, even though additional details were included in the Referral.

        • The parties had clearly invited the adjudicator to determine his own jurisdiction, and he decided that he had jurisdiction — this was binding until final determination.

        • No material breach of natural justice:

          • The adjudicator had fairly considered all jurisdictional objections and provided detailed reasons.

  • On abatement and set-off:

    • Defendant’s arguments about prior overpayments were rejected because under the HGCRA 1996, any such deductions must be properly notified in a compliant withholding notice.

​

  • Outcome:

    • Judgment for £95,383.50 plus agreed interest (£2,215.40), totaling £97,598.90.

    • Costs awarded to Whiteways.

General Principles Developed

  • Jurisdiction of adjudicator:

    • An adjudicator's jurisdiction is determined by the disputes identified in the Notice of Adjudication.

    • Once parties invite an adjudicator to decide jurisdiction (and he does), that decision is binding temporarily and cannot be reopened during enforcement.

​

  • Natural justice:

    • An adjudicator does not breach natural justice merely by expanding upon points included in the referral if they flow from the notice and both parties had an opportunity to respond.

​

  • Abatement and set-off under the HGCRA:

    • No distinction between set-off and abatement regarding notification obligations.

    • All deductions or abatement arguments require valid withholding notices in compliance with s.110 and s.111 of the HGCRA.

    • Without such notices, the paying party cannot later raise abatement or set-off to resist enforcement.

​

  • Finality and enforcement:

    • Courts will robustly enforce adjudication decisions to uphold "pay now, argue later" policy, unless clear jurisdictional or serious natural justice breaches exist.

bottom of page