
Toppan Holdings Ltd & Abbey Healthcare (Mill Hill) Ltd v Augusta 2008 LLP
Citation: [2025] EWHC 1691 (TCC)
Background Facts​
-
Toppan Holdings Ltd were the freeholder of Aarandale Manor Care Home.
-
Abbey Healthcare were the leaseholder and operator of the care home.
-
Augusta 2008 LLP (formerly Simply Construct) were the design and build contractor responsible for the care home's construction.
-
Major fire safety defects discovered in 2018, including inadequate fire resistance, fire stopping, and other construction faults.
-
These defects posed significant safety risks to residents, affecting occupancy, preventing full use of bedrooms, and stopping an anticipated sale of the care home to BlackRock.
-
Extensive remedial works had to be carried out, causing operational disruption and suppressed occupancy.
-
Toppan claimed for loss connected to the aborted BlackRock sale, interest and finance losses.
-
Abbey claimed for loss of trading profits, abortive legal costs, and overdraft charges.
​Judgment
-
Court’s decision:
-
The court found Augusta (Simply) in breach of contract and duty of care due to serious design and construction defects.
-
Accepted that occupancy was suppressed from September 2018 due to the need to prepare for and carry out remedial works, not just from the start of the actual works.
-
Abbey was entitled to claim on a "but for" basis, comparing actual trading profits to hypothetical profits absent defects.
-
​
-
Outcome on damages:
-
Abbey’s loss of trading profits was largely accepted, subject to adjustments reflecting reasonable growth assumptions.
-
Toppan’s claims for loss of sale and associated finance costs were accepted in principle.
-
The court relied heavily on contemporaneous documents and detailed expert evidence from both valuation and accountancy experts.
-
​
-
Credibility of evidence:
-
The factual evidence of Abbey’s finance director and project consultant was preferred; their testimonies were clear and credible.
-
The court criticised Augusta’s lack of factual evidence and reliance on speculative points.
-
General Principles Developed
-
Occupancy impact and mitigation:
-
Where serious defects create health and safety risks, early suppression of occupancy and marketing efforts can be reasonable mitigation, even before physical works start.
-
​
-
"But for" loss of profit analysis:
-
Loss of trading profits can be assessed by comparing actual trading results to carefully modelled hypothetical scenarios that reflect reasonable assumptions about occupancy growth, fee levels, and market conditions.
-
​
-
Importance of contemporaneous documentation:
-
Judges should give significant weight to objective contemporaneous records over reconstructed witness recollections.
-
Consistent with the "Gestmin" approach (importance of documents over memory).
-
​
-
Contractor's notification duties:
-
Contractors must notify insurers promptly when defects and claims arise (relevant to clause 6.13A of the building contract here).
-
​
-
Reliance on expert joint models:
-
Modern approach encourages parties' experts to agree joint models and parameters wherever possible to simplify and clarify damages quantification.
-