top of page

Aspect Contracts (Asbestos) Ltd v Higgins Construction Plc

Citation: [2015] UKSC 38

Background Facts​

  • In 2004, Aspect conducted an asbestos survey and issued a report in April 2004. In 2005, during redevelopment, Higgins discovered asbestos materials not identified in Aspect’s report. Higgins alleged losses due to this omission.

  • ​Higgins referred a claim for £822,482 to adjudication in 2009, alleging breach of contract and/or negligence.

  • The adjudicator awarded Higgins £490,627 plus interest. Aspect paid £658,017 (including interest and costs).

  • Higgins did not commence further proceedings to recover the balance or finalise the dispute.

  • In 2012 (after limitation periods expired), Aspect started court proceedings seeking repayment of the sums it had paid, arguing it had overpaid based on the true merits.

​Judgment

  • Supreme Court decision:

    • Aspect was entitled to bring a claim to recover sums paid under the adjudicator’s decision.

    • This right arose from an implied term in the Scheme for Construction Contracts (or alternatively, on a restitutionary basis).

    • Aspect’s cause of action to recover overpayments ran for six years from the date of payment, not from the original breach.

​

  • Key findings:

    • The adjudicator’s decision is only temporarily binding, pending final determination in litigation, arbitration, or agreement.

    • Aspect’s repayment claim was not time-barred; it fell within six years from its payment in August 2009.

​

  • Outcome:

    • The Supreme Court upheld the Court of Appeal’s ruling that Aspect could pursue its claim for repayment.

    • The case was remitted to determine the substantive merits (whether money was truly owed).

General Principles Developed

  • Temporary nature of adjudicator’s decisions:

    • Adjudication decisions are “interim” and binding only until the dispute is finally determined by court or arbitration.

​

  • Right to final determination:

    • Both paying and receiving parties retain the right to have the underlying dispute finally decided on the merits, regardless of the adjudicator’s provisional decision.

​

  • Implied repayment right:

    • There is an implied contractual term (from the Scheme) that a paying party can recover sums paid if it is later finally determined that no sums were due.

​

  • Limitation periods:

    • For repayment claims based on an adjudication payment, the limitation period runs from the date of payment, not from the original cause of action.

​

  • Cash flow vs final account:

    • The decision supports the policy that adjudication maintains cash flow temporarily but does not preclude eventual true valuation and adjustment.

bottom of page