
Macob Civil Engineering Ltd v Morrison Construction Ltd
Citation: [1999] EWHC 254 (TCC)
Background Facts​
-
Macob was engaged as a subcontractor to carry out groundworks at a retail development site in Carmarthen, South Wales.
-
Macob submitted an interim payment application (Valuation No. 6).
-
Morrison issued a late notice to withhold payment, which was argued to be out of time.
-
Macob referred the dispute to adjudication under the Housing Grants, Construction and Regeneration Act 1996 ("the Act").
-
The adjudicator decided that Morrison should pay Macob £302,366.34 plus interest and costs.
-
Morrison refused to pay, arguing the decision was invalid due to procedural errors and breaches of natural justice.
​Judgment
-
Court’s decision:
-
The adjudicator’s decision was valid and enforceable.
-
Morrison's arguments about procedural breaches did not invalidate the decision at this enforcement stage.
-
​
-
Key findings:
-
The decision of an adjudicator under the Act is binding and must be complied with immediately, even if there are allegations of error.
-
Challenges to the validity of an adjudicator’s decision should be resolved later in final litigation or arbitration — not at the enforcement stage.
-
Morrison’s attempt to stay enforcement proceedings under the Arbitration Act 1996 was rejected.
-
​
-
Outcome:
-
Declaration granted that the adjudicator’s decision was binding until finally determined otherwise.
-
Morrison required to pay the sums awarded.
-
General Principles Developed
-
Binding nature of adjudicator’s decision:
-
Adjudicators’ decisions are temporarily binding, enforceable straightaway, and must be complied with until the dispute is finally resolved by litigation, arbitration, or settlement.
-
Errors of fact, law, or procedural fairness (unless extreme) do not prevent enforcement.
-
​
-
“Pay now, argue later” policy:
-
The case firmly established this principle in UK adjudication law, supporting the rapid cash flow aims of the 1996 Act.
-
​
-
Natural justice challenges:
-
Alleged breaches of natural justice do not generally stop immediate enforcement; they can be addressed in subsequent proceedings.
-
​
-
No right to refuse compliance pending arbitration:
-
Parties cannot use arbitration clauses to delay payment or avoid compliance with adjudicator's decisions.
-
​
-
Enforcement remedies:
-
The court can grant declarations or money judgments to enforce adjudicator’s decisions. Injunctions for payment are generally inappropriate.
-