top of page

Macob Civil Engineering Ltd v Morrison Construction Ltd

Citation: [1999] EWHC 254 (TCC)

Background Facts​

  • Macob was engaged as a subcontractor to carry out groundworks at a retail development site in Carmarthen, South Wales.

  • Macob submitted an interim payment application (Valuation No. 6).

  • Morrison issued a late notice to withhold payment, which was argued to be out of time.

  • Macob referred the dispute to adjudication under the Housing Grants, Construction and Regeneration Act 1996 ("the Act").

  • The adjudicator decided that Morrison should pay Macob £302,366.34 plus interest and costs.

  • Morrison refused to pay, arguing the decision was invalid due to procedural errors and breaches of natural justice.

​Judgment

  • Court’s decision:

    • The adjudicator’s decision was valid and enforceable.

    • Morrison's arguments about procedural breaches did not invalidate the decision at this enforcement stage.

​

  • Key findings:

    • The decision of an adjudicator under the Act is binding and must be complied with immediately, even if there are allegations of error.

    • Challenges to the validity of an adjudicator’s decision should be resolved later in final litigation or arbitration — not at the enforcement stage.

    • Morrison’s attempt to stay enforcement proceedings under the Arbitration Act 1996 was rejected.

​

  • Outcome:

    • Declaration granted that the adjudicator’s decision was binding until finally determined otherwise.

    • Morrison required to pay the sums awarded.

General Principles Developed

  • Binding nature of adjudicator’s decision:

    • Adjudicators’ decisions are temporarily binding, enforceable straightaway, and must be complied with until the dispute is finally resolved by litigation, arbitration, or settlement.

    • Errors of fact, law, or procedural fairness (unless extreme) do not prevent enforcement.

​

  • “Pay now, argue later” policy:

    • The case firmly established this principle in UK adjudication law, supporting the rapid cash flow aims of the 1996 Act.

​

  • Natural justice challenges:

    • Alleged breaches of natural justice do not generally stop immediate enforcement; they can be addressed in subsequent proceedings.

​

  • No right to refuse compliance pending arbitration:

    • Parties cannot use arbitration clauses to delay payment or avoid compliance with adjudicator's decisions.

​

  • Enforcement remedies:

    • The court can grant declarations or money judgments to enforce adjudicator’s decisions. Injunctions for payment are generally inappropriate.

bottom of page