top of page

Hillcrest Homes Ltd v Beresford and Curbishley Ltd

Citation: [2014] EWHC 280 (TCC)

Background Facts​

  • A luxury residential property at Sleepy Hollow, Prestbury, under a JCT Design and Build Contract (2005 Edition).

  • Structural engineer Howard Taylor Associates (HTA) had been appointed by Hillcrest before the building contract.

  • The contract required that HTA be novated (transferred) to B&C so that B&C would assume responsibility for structural design.

  • HTA did not sign the novation agreement until after practical completion, and B&C refused to sign it at all.

  • B&C alleged that Hillcrest misrepresented that novation had been agreed, leading B&C to enter into the contract.

  • B&C commenced adjudication claiming negligent misstatement (misrepresentation) and seeking declarations that novation had not occurred and that the novation deed was void.

  • The adjudicator ruled in B&C’s favour, finding Hillcrest made a negligent misstatement and that there was no effective novation.

​Judgment

  • Jurisdiction and scope:

    • The court held that the adjudicator lacked jurisdiction to determine claims of misrepresentation under the Misrepresentation Act 1967 as these did not arise "under the contract" (Article 7).

​

  • Multiple disputes:

    • The court found that B&C had improperly referred more than one dispute to adjudication without consent, contrary to Article 7.

    • Natural justice:

    • The adjudicator determined the validity of the novation agreement on a legal basis not argued by either party, breaching natural justice.

​

  • Final determination on novation:

    • The court concluded there was no effective novation of HTA to B&C:

    • The Employer’s Requirements envisaged novation at the time of the building contract.

    • HTA signed only after practical completion.

    • Execution by all three parties (Hillcrest, B&C, HTA) as a deed was required but never completed.

​

  • Outcome:

    • The adjudicator’s decision was unenforceable.

    • Hillcrest was not entitled to its declarations.

    • B&C had not wrongfully refused to sign the novation agreement.

General Principles Developed

  • Scope of adjudication ("arising under the contract"):

    • Claims for misrepresentation under the Misrepresentation Act do not fall within "arising under the contract" adjudication clauses, distinguishing such claims from contractual claims.

​

  • Single dispute requirement:

    • Only one dispute can be referred to adjudication unless the parties consent; multiple disputes without consent render an adjudicator’s decision unenforceable.

​

  • Natural justice in adjudication:

    • An adjudicator must not decide a case on grounds not argued by the parties; doing so is a material breach of natural justice.

​

  • Novation formalities:

    • For novation to be effective, there must be clear tripartite agreement, and if contemplated as a deed, all parties must execute it as such.

    • Timing and conditions set out in contract documents are critical.

​

  • No implied breach or estoppel:

    • A contractor is not automatically in breach for failure to procure novation unless expressly required by contract.

    • Estoppel arguments require clear representations and detrimental reliance, which were not found here.

bottom of page