
Hillcrest Homes Ltd v Beresford and Curbishley Ltd
Citation: [2014] EWHC 280 (TCC)
Background Facts​
-
A luxury residential property at Sleepy Hollow, Prestbury, under a JCT Design and Build Contract (2005 Edition).
-
Structural engineer Howard Taylor Associates (HTA) had been appointed by Hillcrest before the building contract.
-
The contract required that HTA be novated (transferred) to B&C so that B&C would assume responsibility for structural design.
-
HTA did not sign the novation agreement until after practical completion, and B&C refused to sign it at all.
-
B&C alleged that Hillcrest misrepresented that novation had been agreed, leading B&C to enter into the contract.
-
B&C commenced adjudication claiming negligent misstatement (misrepresentation) and seeking declarations that novation had not occurred and that the novation deed was void.
-
The adjudicator ruled in B&C’s favour, finding Hillcrest made a negligent misstatement and that there was no effective novation.
​Judgment
-
Jurisdiction and scope:
-
The court held that the adjudicator lacked jurisdiction to determine claims of misrepresentation under the Misrepresentation Act 1967 as these did not arise "under the contract" (Article 7).
-
​
-
Multiple disputes:
-
The court found that B&C had improperly referred more than one dispute to adjudication without consent, contrary to Article 7.
-
Natural justice:
-
The adjudicator determined the validity of the novation agreement on a legal basis not argued by either party, breaching natural justice.
-
​
-
Final determination on novation:
-
The court concluded there was no effective novation of HTA to B&C:
-
The Employer’s Requirements envisaged novation at the time of the building contract.
-
HTA signed only after practical completion.
-
Execution by all three parties (Hillcrest, B&C, HTA) as a deed was required but never completed.
-
​
-
Outcome:
-
The adjudicator’s decision was unenforceable.
-
Hillcrest was not entitled to its declarations.
-
B&C had not wrongfully refused to sign the novation agreement.
-
General Principles Developed
-
Scope of adjudication ("arising under the contract"):
-
Claims for misrepresentation under the Misrepresentation Act do not fall within "arising under the contract" adjudication clauses, distinguishing such claims from contractual claims.
-
​
-
Single dispute requirement:
-
Only one dispute can be referred to adjudication unless the parties consent; multiple disputes without consent render an adjudicator’s decision unenforceable.
-
​
-
Natural justice in adjudication:
-
An adjudicator must not decide a case on grounds not argued by the parties; doing so is a material breach of natural justice.
-
​
-
Novation formalities:
-
For novation to be effective, there must be clear tripartite agreement, and if contemplated as a deed, all parties must execute it as such.
-
Timing and conditions set out in contract documents are critical.
-
​
-
No implied breach or estoppel:
-
A contractor is not automatically in breach for failure to procure novation unless expressly required by contract.
-
Estoppel arguments require clear representations and detrimental reliance, which were not found here.
-