
Carrington v American International Group UK Ltd
Citation: [2025] EWHC 1010 (TCC)
Background Facts​
-
Ms Carrington engaged Mr Godfrey in 2010 to provide full architectural and contract administration services for substantial refurbishment and extension works on her coastal home.
-
The contractor (Ease Development Services) was appointed under a JCT Minor Works Contract for ~£231,000.
-
Alleged inadequate design and incomplete or missing construction details.
-
Works started in 2012 but were not completed; the contractor left in 2013 citing lack of information and payment issues.
-
Ms Carrington claimed major defects, uninhabitable conditions, and that she was forced to move out in 2015.
-
Complex, protracted procedural history with multiple attempts to amend particulars of claim, focusing on allegations of design failures, failure to inspect, and failure to issue instructions.
​Judgment
-
Main issues decided:
-
Whether the Claimant's latest amended claim should proceed or be struck out or subject to summary judgment for lacking a real prospect of success.
-
Defendant argued failure to plead causation properly and that some claims were statute-barred.
-
​
-
Court’s decision:
-
Allowed most of the claim to proceed to trial.
-
The Judge found that Ms Carrington had at least a "reasonably arguable" case on the core allegations, particularly:
-
Alleged duty to review design and issue adequate construction information.
-
Potential causation and loss arguments (though challenging factually).
-
The court rejected the Defendant’s argument that certain causation arguments had no real prospect.
-
One discrete part of the claim (regarding failure to inspect and certify interim payments) was identified as defective, but overall, strike-out and summary judgment were refused.
-
​
-
Key procedural ruling:
-
Claimant was allowed to continue despite previous deficiencies in her pleadings and procedural delays, emphasizing the right to have complex factual disputes resolved at trial.
-
General Principles Developed
-
Duty to review and supervise:
-
An architect or contract administrator may have a duty to review and, where necessary, provide further design information even if they believe initial drawings are sufficient.
-
This duty is potentially ongoing, particularly when issues are raised by the contractor on site.
-
​
-
Causation approach:
-
Courts reaffirm that in professional negligence, causation involves what the professional should have done, not merely what they would have done (referencing Bolitho and Coudert cases).
-
Even if a contractor continues work despite known deficiencies, the design professional may still be held causatively liable.
-
​
-
Complex causation and contribution:
-
When losses involve multiple parties (e.g., designer and contractor), issues of causation and relative responsibility are fact-sensitive and generally unsuitable for summary judgment.
-
​
-
Pleading standards:
-
Claimants must provide detailed pleadings, but courts may still allow claims to proceed where they set out an arguable case, especially in complex technical disputes.
-
​
-
Limitation and continuing duties:
-
Breaches of ongoing duties (e.g., during construction) can restart limitation periods even if initial design duties are time-barred.
-