top of page

Carrington v American International Group UK Ltd

Citation: [2025] EWHC 1010 (TCC)

Background Facts​

  • Ms Carrington engaged Mr Godfrey in 2010 to provide full architectural and contract administration services for substantial refurbishment and extension works on her coastal home.

  • The contractor (Ease Development Services) was appointed under a JCT Minor Works Contract for ~£231,000.

  • Alleged inadequate design and incomplete or missing construction details.

  • Works started in 2012 but were not completed; the contractor left in 2013 citing lack of information and payment issues.

  • Ms Carrington claimed major defects, uninhabitable conditions, and that she was forced to move out in 2015.

  • Complex, protracted procedural history with multiple attempts to amend particulars of claim, focusing on allegations of design failures, failure to inspect, and failure to issue instructions.

​Judgment

  • Main issues decided:

    • Whether the Claimant's latest amended claim should proceed or be struck out or subject to summary judgment for lacking a real prospect of success.

    • Defendant argued failure to plead causation properly and that some claims were statute-barred.

​

  • Court’s decision:

    • Allowed most of the claim to proceed to trial.

    • The Judge found that Ms Carrington had at least a "reasonably arguable" case on the core allegations, particularly:

    • Alleged duty to review design and issue adequate construction information.

    • Potential causation and loss arguments (though challenging factually).

    • The court rejected the Defendant’s argument that certain causation arguments had no real prospect.

    • One discrete part of the claim (regarding failure to inspect and certify interim payments) was identified as defective, but overall, strike-out and summary judgment were refused.

​

  • Key procedural ruling:

    • Claimant was allowed to continue despite previous deficiencies in her pleadings and procedural delays, emphasizing the right to have complex factual disputes resolved at trial.

General Principles Developed

  • Duty to review and supervise:

    • An architect or contract administrator may have a duty to review and, where necessary, provide further design information even if they believe initial drawings are sufficient.

    • This duty is potentially ongoing, particularly when issues are raised by the contractor on site.

​

  • Causation approach:

    • Courts reaffirm that in professional negligence, causation involves what the professional should have done, not merely what they would have done (referencing Bolitho and Coudert cases).

    • Even if a contractor continues work despite known deficiencies, the design professional may still be held causatively liable.

​

  • Complex causation and contribution:

    • When losses involve multiple parties (e.g., designer and contractor), issues of causation and relative responsibility are fact-sensitive and generally unsuitable for summary judgment.

​

  • Pleading standards:

    • Claimants must provide detailed pleadings, but courts may still allow claims to proceed where they set out an arguable case, especially in complex technical disputes.

​

  • Limitation and continuing duties:

    • Breaches of ongoing duties (e.g., during construction) can restart limitation periods even if initial design duties are time-barred.

bottom of page