
Universal Sealants (UK) Ltd (t/a USL Bridgecare) v Sanders Plant And Waste Management Ltd
Citation: [2019] EWHC 2360 (TCC)
Background Facts​
-
Universal Sealants (UK) Ltd ("USL"), trading as USL Bridgecare, were a specialist contractor.
-
Sanders Plant and Waste Management Ltd ("Sanders"), were supplier of concrete.
-
USL was engaged to carry out works on the A1 Blaydon Haugh Viaduct in Gateshead.
-
USL ordered concrete from Sanders, specifying grade M50 concrete.
-
Sanders delivered concrete, but instead of M50 grade, they supplied ST5 grade, which was unfit for the intended purpose.
-
The concrete had to be broken out and replaced, causing additional costs.
-
USL claimed Sanders was in breach of contract for supplying the wrong concrete.
-
An adjudicator awarded USL £52,259 in damages.
-
Sanders resisted enforcement, arguing the adjudicator lacked jurisdiction because:
-
The contract did not contain an adjudication clause, and the statutory scheme should not apply.
-
The supply fell under an exclusion in s.105(2)(d) of the Housing Grants, Construction and Regeneration Act 1996 (HGCRA).
-
​Judgment
-
Outcome:
-
Summary judgment was refused; enforcement was denied.
-
​
-
Key findings:
-
There was a real prospect of success in Sanders’ defence based on statutory exclusion under s.105(2)(d).
-
Section 105(2)(d) excludes contracts for the supply of materials (including concrete) unless they also provide for installation.
-
The court found that, although the concrete was delivered and poured into a channel, this did not amount to an "installation" under the Act — it was part of the delivery process.
-
Therefore, Sanders’ supply contract likely fell outside the definition of a "construction contract" under the Act, meaning the adjudicator had no jurisdiction.
-
General Principles Developed
-
Scope of "construction operations" under HGCRA:
-
Contracts solely for supply and delivery of materials fall outside the statutory adjudication regime unless they include installation obligations.
-
Delivery and immediate pouring of concrete on-site do not necessarily constitute "installation" — especially if no separate work or finishing is done by the supplier after delivery.
-
​
-
Adjudicator’s jurisdiction:
-
An adjudicator only has jurisdiction if there is a construction contract within the meaning of s.104 HGCRA.
-
A party may resist enforcement by showing that the statutory adjudication framework did not apply because of exclusions.
-
​
-
"Installation" interpretation:
-
"Installation" requires more than mere delivery or placement; it implies active work on or with the material beyond straightforward delivery.
-
​
-
Contract formation and acceptance:
-
Silence or delivery in response to a purchase order may constitute acceptance by conduct, but issues of contract terms and scope remain relevant to jurisdiction questions.
-
​
-
Enforcement approach:
-
Courts will refuse to enforce adjudication decisions where there is a genuine jurisdictional challenge with a real prospect of success.
-