top of page

Camillin Denny Architects Ltd v Adelaide Jones & Co Ltd

Citation: [2009] EWHC 2110 (TCC)

Background Facts

  • Parties:

    • Claimant: Camillin Denny Architects Ltd ("CDA"), an architectural services provider.

    • Defendant: Adelaide Jones & Co Ltd ("AJ"), a project manager.

​

  • Project:
    Refurbishment and extension of a Grade I listed building at 10 Hertford Street, Mayfair, London.

​

  • Contract:
    CDA was appointed by AJ in February 2008 for architectural design services under a contract worth £425,000, potentially adjusted if project costs increased.

​

  • Dispute:

    • There were discussions in 2008 about novating the contract to a new company called "Euro Constructions," allegedly set up by a third-party financier, Mr Lohia.

    • CDA issued invoices to Euro Constructions, but no formal novation agreement was executed.

    • AJ later purported to terminate CDA's appointment on behalf of Euro Constructions.

    • CDA commenced adjudication against AJ for unpaid fees; the adjudicator awarded CDA £76,905 plus interest and costs.

    • AJ challenged enforcement, arguing there was a novation and that the adjudicator had no jurisdiction.

​Judgment

  • Key findings:

    • There was no effective novation: The court found no clear evidence that Euro Constructions had accepted the novation, no signed agreement, and no proper incorporation evidence.

    • The original contract with AJ remained in place throughout.

    • The adjudicator was entitled to determine if there was a novation as part of the substantive dispute.

    • AJ’s claim of adjudicator bias and breach of natural justice (due to costs decisions) was dismissed. The adjudicator acted fairly and within his discretion.

​

  • Outcome:

    • The court enforced the adjudicator's decision, ordering AJ to pay CDA the awarded sums.

    • AJ's jurisdiction and natural justice defences failed.

    • CDA was awarded costs, but assessed on a standard basis with some reduction.

General Principles Developed

  • Strict standard for proving novation:
    A valid novation requires clear agreement by all parties, including the incoming party. Mere discussions or draft proposals are insufficient.

​

  • Jurisdiction to decide preliminary issues:
    An adjudicator validly appointed can decide whether the contract remains in place and whether jurisdiction exists if these questions are part of the referred dispute.

​

  • Enforcement policy:
    Courts will robustly enforce adjudicators' decisions, even if they might be factually or legally incorrect, unless there is a plain lack of jurisdiction or a serious breach of natural justice.

​

  • Natural justice threshold:
    Complaints about adjudicators' procedural decisions (such as costs) rarely succeed. The court confirmed that fairness does not mean correctness.

​

  • Cash flow policy of adjudication:
    The judgment reinforced the principle that adjudication is designed to maintain cash flow, with disputes about correctness to be resolved later by final proceedings.

bottom of page