
Octoesse LLP v Trak Special Projects Ltd
Citation: [2016] EWHC 3180 (TCC)
Background Facts
-
The project involved the construction of residential and retail units in Long Acre, London, under a JCT Intermediate Building Contract 2011.
-
Original completion date: 22 September 2013 (likely meant to be 2014), later extended.
-
Practical completion achieved: 13 February 2015.
-
Certificate of non-completion issued: 3 October 2014.
-
Further extension of time granted: 9 November 2015, cancelling prior non-completion certificate.
-
After final certification, Octoesse issued a pay less notice deducting £89,250 in liquidated damages. Trak argued that the deduction was invalid because no valid certificate of non-completion existed after the extension of time, as required under clauses 2.22 and 2.23.
-
Trak succeeded; the adjudicator ruled that the pay less notice was invalid, ordered Octoesse to pay £59,991.83 plus interest. Octoesse started Part 8 proceedings challenging the adjudicator's decision.
Judgment
-
Clauses considered:
-
Clause 2.22: Requires a certificate of non-completion if the contractor fails to finish by the completion date. If an extension of time is granted, this cancels any existing non-completion certificate.
-
Clause 2.23: Allows deduction of liquidated damages only if a valid non-completion certificate exists.
-
​
-
Key findings:
-
The extension of time granted in November 2015 cancelled the prior certificate of non-completion.
-
No new certificate of non-completion was issued after that extension.
-
As a result, Octoesse was not entitled to deduct liquidated damages because the contractual preconditions were not satisfied.
-
​
-
Outcome:
The court upheld the adjudicator’s decision and ordered Octoesse to pay the sums awarded. Octoesse’s request for declarations and to overturn the adjudication result was rejected.
General Principles Developed
-
Strict compliance with contractual notice mechanisms:
Deduction of liquidated damages is only possible if all procedural and contractual preconditions (like a valid certificate of non-completion) are strictly met.
​
-
Effect of extensions of time:
Granting an extension automatically cancels any existing non-completion certificate, reinforcing the requirement for precise and updated documentation.
​
-
Mandatory interpretation of contractual "shall" provisions:
Courts interpret "shall" as imposing a strict obligation rather than discretionary compliance.
​
-
Importance of accurate administrative steps:
The decision highlights that failure to reissue certificates after extensions can eliminate the right to liquidated damages, even if the contractor was previously in delay.