
M Davenport Builders Ltd v Greer & Anor
Citation: [2019] EWHC 318 (TCC)
Background Facts​
-
Davenport carried out construction works at a residential property in Stockport, under a contract where the Scheme for Construction Contracts (1998) applied (since no express payment or adjudication terms existed).
-
Davenport issued a final account application for £106,160.84 on 22 June 2018. The Greers failed to serve a valid payment notice or pay less notice within the statutory timeframes.
-
An adjudication by Mr Sutcliffe awarded Davenport the full sum plus interest. The Greers did not pay.
-
​The Greers later commenced a "true value" adjudication with a second adjudicator (Mr Sliwinski), who valued the works at a lower sum and decided no further payment was due.
-
The Greers tried to rely on this later decision to resist enforcement of the first adjudicator’s award.
​Judgment
-
Decision:
-
The court granted summary judgment enforcing the first adjudicator’s decision in full.
-
​
-
Key findings:
-
The Greers were required to pay the sum awarded by the first adjudicator before they could commence or rely on a "true value" adjudication.
-
Section 111 of the Housing Grants, Construction and Regeneration Act 1996 (HGCRA) imposes an immediate payment obligation where no valid payment or pay less notice is served.
-
The Greers had not paid the first adjudication award and therefore could not rely on the second adjudication as a defence or set-off.
-
​
-
Outcome:
-
Davenport awarded £106,160.84 plus interest.
-
Costs awarded to Davenport.
-
General Principles Developed
-
"Pay now, argue later" reinforced:
-
Parties must comply with adjudicator awards immediately, even if they intend to challenge the valuation later.
-
They can only pursue a "true value" adjudication after paying the notified sum.
-
​
-
No right to set-off before payment:
-
A paying party cannot use a subsequent valuation adjudication as a set-off or defence to avoid payment of a prior adjudication award.
-
​
-
Policy emphasis on cash flow:
-
The court reaffirmed that the primary purpose of the 1996 Act is to maintain cash flow to contractors and subcontractors, supporting prompt interim payments.
-
​
-
Clarification of sequencing:
-
The judgment clarified that while a "true value" adjudication is permitted, it does not suspend or replace the requirement to pay sums due under a "smash and grab" adjudication first.
-
​
-
Consistency with Grove and Harding:
-
The decision builds on the Court of Appeal’s decisions in S&T (UK) Ltd v Grove Developments Ltd and Harding v Paice, confirming that compliance with immediate payment obligations precedes valuation rights.
-