top of page

M Davenport Builders Ltd v Greer & Anor

Citation: [2019] EWHC 318 (TCC)

Background Facts​

  • Davenport carried out construction works at a residential property in Stockport, under a contract where the Scheme for Construction Contracts (1998) applied (since no express payment or adjudication terms existed).

  • Davenport issued a final account application for £106,160.84 on 22 June 2018. The Greers failed to serve a valid payment notice or pay less notice within the statutory timeframes.

  • An adjudication by Mr Sutcliffe awarded Davenport the full sum plus interest. The Greers did not pay.

  • ​The Greers later commenced a "true value" adjudication with a second adjudicator (Mr Sliwinski), who valued the works at a lower sum and decided no further payment was due.

  • The Greers tried to rely on this later decision to resist enforcement of the first adjudicator’s award.

​Judgment

  • Decision:

    • The court granted summary judgment enforcing the first adjudicator’s decision in full.

​

  • Key findings:

    • The Greers were required to pay the sum awarded by the first adjudicator before they could commence or rely on a "true value" adjudication.

    • Section 111 of the Housing Grants, Construction and Regeneration Act 1996 (HGCRA) imposes an immediate payment obligation where no valid payment or pay less notice is served.

    • The Greers had not paid the first adjudication award and therefore could not rely on the second adjudication as a defence or set-off.

​

  • Outcome:

    • Davenport awarded £106,160.84 plus interest.

    • Costs awarded to Davenport.

General Principles Developed

  • "Pay now, argue later" reinforced:

    • Parties must comply with adjudicator awards immediately, even if they intend to challenge the valuation later.

    • They can only pursue a "true value" adjudication after paying the notified sum.

​

  • No right to set-off before payment:

    • A paying party cannot use a subsequent valuation adjudication as a set-off or defence to avoid payment of a prior adjudication award.

​

  • Policy emphasis on cash flow:

    • The court reaffirmed that the primary purpose of the 1996 Act is to maintain cash flow to contractors and subcontractors, supporting prompt interim payments.

​

  • Clarification of sequencing:

    • The judgment clarified that while a "true value" adjudication is permitted, it does not suspend or replace the requirement to pay sums due under a "smash and grab" adjudication first.

​

  • Consistency with Grove and Harding:

    • The decision builds on the Court of Appeal’s decisions in S&T (UK) Ltd v Grove Developments Ltd and Harding v Paice, confirming that compliance with immediate payment obligations precedes valuation rights.

bottom of page