top of page

Bilton & Johnson (Building) Co Ltd v Three Rivers Property Investments Ltd

Citation: [2022] EWHC 53 (TCC)

Background Facts​

  • Works concerned the refurbishment of an industrial estate in Oxfordshire under a JCT Design and Build Contract 2016.

  • The initial tender (August 2018) included phased completion dates and separate liquidated damages rates for each section.

  • Later, a "Signed Contract" dated January 2019 provided a single completion date and a simplified liquidated damages clause (£2,500 per week overall).

  • TRP withheld £234,641.56 in liquidated damages, arguing entitlement to £2,500 per section per week.

  • BJB disputed this, arguing that under the signed contract, only £2,500 per week in total applied and TRP’s withholding exceeded what was contractually due.

  • The adjudicator decided in BJB’s favour, awarding repayment of £228,273.48 plus interest and costs, after finding that TRP was entitled only to minimal damages.

​Judgment

  • Court's decision:

    • Summary judgment was granted enforcing the adjudicator's decision.

    • The defendant's arguments that the adjudicator had acted in breach of natural justice or failed to consider its rectification defence were rejected.

​

  • Key points:

    • The adjudicator properly considered the competing contractual documents and concluded the final signed contract superseded earlier drafts.

    • The adjudicator did consider TRP's rectification defence in detail and rejected it, finding that even if a drafting mistake had occurred, the higher liquidated damages rate would have been an unenforceable penalty.

​

  • Outcome:

    • BJB’s enforcement application succeeded in full.

    • TRP was ordered to pay the adjudicated sum plus interest.

General Principles Developed

  • Enforcement of adjudication decisions:

    • Reinforces the robust approach of English courts to enforcing adjudicators’ decisions promptly (“pay now, argue later”).

    • Courts will not interfere merely because of alleged errors in law or procedure unless there is a clear jurisdictional error or serious breach of natural justice.

​

  • Natural justice in adjudication:

    • Adjudicators must give parties a fair opportunity to address key issues but do not need to consult on every element of their reasoning.

    • If the adjudicator’s reasoning is derived from arguments before them, there is generally no breach.

​

  • Rectification defences:

    • Where a party argues rectification to correct an alleged drafting mistake, they must establish it clearly and show entitlement before relying on the corrected term.

    • The adjudicator is not empowered to grant rectification unless expressly agreed or supported by clear authority.

​

  • Penalty clauses:

    • Even if a rectification claim might theoretically succeed, liquidated damages that are “extravagantly disproportionate” to legitimate interests will be unenforceable as penalties.

​

  • Contract formation and supersession:

    • A signed contract can supersede earlier tender-stage or draft contractual documents even if those earlier versions contained different provisions.

bottom of page