
Bilton & Johnson (Building) Co Ltd v Three Rivers Property Investments Ltd
Citation: [2022] EWHC 53 (TCC)
Background Facts​
-
Works concerned the refurbishment of an industrial estate in Oxfordshire under a JCT Design and Build Contract 2016.
-
The initial tender (August 2018) included phased completion dates and separate liquidated damages rates for each section.
-
Later, a "Signed Contract" dated January 2019 provided a single completion date and a simplified liquidated damages clause (£2,500 per week overall).
-
TRP withheld £234,641.56 in liquidated damages, arguing entitlement to £2,500 per section per week.
-
BJB disputed this, arguing that under the signed contract, only £2,500 per week in total applied and TRP’s withholding exceeded what was contractually due.
-
The adjudicator decided in BJB’s favour, awarding repayment of £228,273.48 plus interest and costs, after finding that TRP was entitled only to minimal damages.
​Judgment
-
Court's decision:
-
Summary judgment was granted enforcing the adjudicator's decision.
-
The defendant's arguments that the adjudicator had acted in breach of natural justice or failed to consider its rectification defence were rejected.
-
​
-
Key points:
-
The adjudicator properly considered the competing contractual documents and concluded the final signed contract superseded earlier drafts.
-
The adjudicator did consider TRP's rectification defence in detail and rejected it, finding that even if a drafting mistake had occurred, the higher liquidated damages rate would have been an unenforceable penalty.
-
​
-
Outcome:
-
BJB’s enforcement application succeeded in full.
-
TRP was ordered to pay the adjudicated sum plus interest.
-
General Principles Developed
-
Enforcement of adjudication decisions:
-
Reinforces the robust approach of English courts to enforcing adjudicators’ decisions promptly (“pay now, argue later”).
-
Courts will not interfere merely because of alleged errors in law or procedure unless there is a clear jurisdictional error or serious breach of natural justice.
-
​
-
Natural justice in adjudication:
-
Adjudicators must give parties a fair opportunity to address key issues but do not need to consult on every element of their reasoning.
-
If the adjudicator’s reasoning is derived from arguments before them, there is generally no breach.
-
​
-
Rectification defences:
-
Where a party argues rectification to correct an alleged drafting mistake, they must establish it clearly and show entitlement before relying on the corrected term.
-
The adjudicator is not empowered to grant rectification unless expressly agreed or supported by clear authority.
-
​
-
Penalty clauses:
-
Even if a rectification claim might theoretically succeed, liquidated damages that are “extravagantly disproportionate” to legitimate interests will be unenforceable as penalties.
-
​
-
Contract formation and supersession:
-
A signed contract can supersede earlier tender-stage or draft contractual documents even if those earlier versions contained different provisions.
-