
Parkwood Leisure Ltd v Laing O'Rourke Wales and West Ltd
Citation: [2013] EWHC 2665 (TCC)
Background Facts​
-
Parties & project:
-
Parkwood Leisure Ltd (Parkwood): operator of Cardiff International Pool, holding a sub-lease and operating agreement.
-
Laing O’Rourke Wales and West Ltd (LORWW): design-and-build contractor for the pool.
-
​
-
Works & warranties:
-
LORWW entered into a design-and-build contract in 2006 with Orion (the employer) to design and construct the pool.
-
Under Article 10 of the contract, LORWW issued a collateral warranty to Parkwood in December 2007, warranting proper completion and compliance with standards.
-
​
-
Defects & disputes:
-
Parkwood later identified serious issues with air handling units (AHUs), leading to humidity problems, staining, corrosion, and operational difficulties.
-
There was a Settlement Agreement in 2012 resolving certain previous AHU-related issues but allowing new claims relating to new matters.
-
In 2013, Parkwood served a new claim for defective AHUs, alleging inherent design flaws and seeking substantial damages.
-
​
-
Legal question:
Parkwood wanted to adjudicate under the Housing Grants, Construction and Regeneration Act 1996 (HGCRA). It needed a determination that the collateral warranty was a "construction contract" under the Act to have adjudication rights.
​Judgment
-
Collateral warranty as a construction contract:
-
The court held that the collateral warranty was a "construction contract" under the HGCRA.
-
The warranty contained express obligations to "carry out and complete" the works in accordance with the contract, not just retrospective promises about past work.
-
​
-
Settlement Agreement issues:
-
The parties agreed that some AHU claims were settled in 2012.
-
The court did not definitively resolve whether the new 2013 AHU claims were compromised; it noted that further factual analysis would be needed.
-
However, Parkwood was entitled to argue these points substantively later, and the court gave declarations reflecting the parties' agreed positions.
-
​
-
Outcome:
-
Declaration granted that the collateral warranty was a construction contract, allowing Parkwood to adjudicate.
-
Declarations as to the settlement were issued as agreed by counsel.
-
General Principles Developed
-
Collateral warranties as construction contracts:
-
A collateral warranty can be a "construction contract" if it includes ongoing obligations to carry out and complete works, not merely retrospective assurances.
-
This depends on the wording — especially the use of active terms such as "warrants", "undertakes", "acknowledges" covering future performance.
-
​
-
Adjudication rights extended:
-
Beneficiaries of such collateral warranties can access adjudication under the HGCRA if their warranty qualifies as a construction contract.
-
​
-
Effect of settlement agreements on future claims:
-
Settlement agreements must be carefully drafted to clarify whether future or separate claims are excluded.
-
New or separate issues arising after a settlement may not automatically be barred, especially where new defects or factual bases arise.
-
​
-
Practical drafting lessons:
-
Clear distinction in warranties between purely historic (past state) obligations and future performance obligations.
-
Careful definitions in settlement agreements to avoid unintended release or exclusion of future claims.
-